BBC SPORT Arabic Spanish Russian Chinese
BBCi NEWS   SPORT   WEATHER   WORLD SERVICE   A-Z INDEX    SEARCH 

BBC Sport
 You are in: Special Events: 2001: Search for a New Wembley  
Sport Front Page
-------------------
Football
Cricket
Rugby Union
Rugby League
Tennis
Golf
Motorsport
Boxing
Athletics
Other Sports
-------------------
Special Events
-------------------
Sports Talk
-------------------
BBC Pundits
TV & Radio
Question of Sport
-------------------
Photo Galleries
Funny Old Game
-------------------
Around The UK: 
N Ireland
Scotland
Wales

BBC Sport Academy
BBC News
BBC Weather
SERVICES
-------------
LANGUAGES
EDITIONS

Thursday, 26 September, 2002, 15:47 GMT 16:47 UK
Countdown to new Wembley
A computer-generated image of the Wembley redevelopment
The clock is ticking down for the new Wembley
Football Association officials hope the new Wembley will be completed by early 2006.

By 2011, they forecast it will be turning in annual profits of 20m.

Below is the countdown to the completion of the new home for English football.


  • Sept 2002-March 2003: The old Wembley will be slowly demolished with the help of specially built mechanical shears. The special scissor-type construction is the largest of its kind and has been specially built for the Wembley demolition.

  • Nov 2002-late 2003: The piling of the foundations for the new stadium will begin to be put in place as soon as sufficient space is cleared by the demolition of the old Wembley.

  • Late 2003-late 2004: Most of the substructure should be in place and work will begin on the steel frame that will form the skeleton of the new stadium. New terracing will also begin to appear.

  • Late 2003-mid 2004: The now-famous arch will be assembled on the southern side of the site and rotated into place.

  • Late 2004: The fit-out of the stadium gets underway in earnest with materials for the changing rooms, toilets and restaurants all arriving on site. Up to 1,500 people are expected to be work on the stadium by this point.

  • Early-mid 2005: With the roof structure completed, the arch is permanently fixed at an angle of 68 degrees.

  • Mid-late 2005: The seats arrive and the stadium should really begin to take shape. The complex web of heating and drainage pipes for the all-important pitch will also be put in place.

  • Early 2006: The stadium opens in three stages, beginning with smaller events to test safety and emergency procedures; a second event to open the second tier and, finally, a high-profile event, hopefully an England international, to have the stadium fully functioning and in all its glory.


  • Latest news

    Background

    Photo gallery

    Have your say

    The old Wembley

    Internet link
    Links to more Search for a New Wembley stories are at the foot of the page.


    E-mail this story to a friend

    Links to more Search for a New Wembley stories

    © BBC ^^ Back to top

    Sport Front Page | Football | Cricket | Rugby Union | Rugby League |
    Tennis | Golf | Motorsport | Boxing | Athletics | Other Sports |
    Special Events | Sports Talk | BBC Pundits | TV & Radio | Question of Sport |
    Photo Galleries | Funny Old Game | N Ireland | Scotland | Wales