Firms criticised over Wembley row

Wembley stadium

A Darlington-based steel contractor and a building firm have been criticised for not reaching an earlier settlement in what became a bitter legal dispute.

The High Court had earlier ruled that Cleveland Bridge was in breach of contract after walking off the Wembley Stadium project in August 2004.

Multiplex Construction secured a £6m judgement against the sub-contractor.

However, the Australian-owned firm also sought damages and the ensuing court battle led to legal costs put at £22m.

£1m photocopying bill

Despite winning the case, Multiplex now faces a £10m legal bill after the judge found against it on some points.

Two years ago the two sides were urged to reach agreement through mediation, but the dispute continued, with each side fielding a team of experts, solicitors, leading counsel and two or three junior counsel.

There were two rounds of preliminary issues, two trips to the Court of Appeal, various amendments to the pleadings and finally a three-month trial of valuation and damages issues.


"Each party has thrown away golden opportunities to settle this litigation upon favourable terms"

Mr Justice Jackson


The cost of photocopying alone was estimated at £1m.

Sitting at the Technology and Construction Court, Mr Justice Jackson said at the end of his final 200-page judgment on Monday: "All thoughts of reaching a sensible settlement were seemingly jettisoned.

"The final result of this litigation is such that (when costs are taken into account) neither party has gained any significant financial benefit.

"Instead large sums of costs and a large amount of management time have been expended on both sides to no useful purpose."

He said that both parties had a measure of responsibility for the situation.

"Over the last two years both parties have brushed aside repeated judicial observations on the wisdom of settling this particular litigation," he added.

"Each party has thrown away golden opportunities to settle this litigation upon favourable terms.

"The lesson for the future which may be drawn from this litigation is that parties would be well advised to use the dispute resolution service offered by the Technology and Construction Court in a more conventional and commercial manner than has been adopted in this case."



E-mail this to a friend
Related to this story:
Wembley firm 'will seek damages' (06 Jun 06 |  Business )
Ruling on Wembley stadium dispute (05 Jun 06 |  London )
Wembley builders in court battle (25 Apr 06 |  Business )

RELATED INTERNET LINKS
Cleveland Bridge
Multiplex
HM Courts Service
The BBC is not responsible for the content of external internet sites



SEARCH BBC NEWS: 

News Front Page | Africa | Americas | Asia-Pacific | Europe | Middle East | South Asia | UK | Business | Health | Science & Environment | Technology | Entertainment | Also in the news | Have Your Say |
UK Contents:  England | Northern Ireland | Scotland | Wales | UK Politics | Education | Magazine

NewsWatch | Notes | Contact us | About BBC News | Profiles | History

^ Back to top | BBC Sport Home | BBC Homepage | Contact us | Help | ©