Axed M4 relief road 'cost 15m'

Coldra roundabout
The route would have bypassed a busy section of the M4 around Newport

More than £15m was spent on research for a proposed M4 relief road around Newport before it was scrapped as "unaffordable", say the Conservatives.

Deputy First Minister Ieuan Wyn Jones axed the planned £1bn route in July, saying its estimated costs had soared.

But the Conservatives said the millions spent showed the previous commitment to the scheme and it was now a "waste".

The assembly government said much of the feasibility work could be used in alternative schemes planned for the M4.

Mr Jones, who also holds the transport portfolio, announced the proposed 14 mile (22.5km) road from Magor to Castleton in September 2007, saying it could open in 2013.

The announcement was against the background of two fatal crashes in previous months which caused gridlock to the south Wales corridor, prompting business leaders to say traffic congestion was hitting the area's economy.

But in July this year, the proposed M4 relief road was dropped from the assembly government's five-year transport plan.

It is clear that even as recently as last year the assembly government was committed to its development and was spending millions on turning it into a reality
William Graham AM

The figures obtained by South East Wales AM William Graham showed £15.5m was spent on the design development of the Magor to Castleton route between 1998 and 2008, with around half of that in the previous two years.

Of the £8.4m spent in the previous two years, nearly £700,000 went on surveys and £7.1m to technical advisers.

Mr Graham said: "The proposed M4 relief road was one of two major strategic requirements for the transport network in south east Wales.

'Wasted'

"It is clear that even as recently as last year the assembly government was committed to its development and was spending millions on turning it into a reality.

"While we accept that major projects such as this inevitably require careful planning over a number of years £15m has effectively been wasted by the assembly government's decision to abandon it."

He called on Mr Jones to say whether his decision was taken in the weeks or months before July this year.

Mr Graham added: "Or was he being advised to scrap it last year, at the same time as spending on its development was higher than all but one of the previous 10 years?"

The Welsh Assembly Government said: "The money spent from 1998 included a considerable amount of work to determine the feasibility of the scheme.

'Practical improvements'

"Much of this work can now be used in the delivery of alternative schemes along this major route.

"The massive escalation in construction costs for the relief road, from an estimated £340m in 1998 to approximately a billion pounds today, has made this scheme unviable.

"However we will be implementing a series of practical improvements along this main corridor to ensure that businesses and individuals using this route will benefit from improved traffic flow at considerably less cost."



Print Sponsor


SEE ALSO
M4 and airport road plans dropped
15 Jul 09 |  Wales
Groups call for congestion charge
15 Jul 09 |  Wales politics
M4 relief road 'could open 2013'
20 Sep 07 |  Wales
New estates 'car-free' play idea
11 Mar 09 |  Wales
Transport group's 350m blueprint
06 Jan 09 |  Wales
M4 relief road fears highlighted
29 Jan 08 |  Wales

RELATED INTERNET LINKS
The BBC is not responsible for the content of external internet sites


FEATURES, VIEWS, ANALYSIS
Has China's housing bubble burst?
How the world's oldest clove tree defied an empire
Why Royal Ballet principal Sergei Polunin quit

BBC navigation

BBC © 2014 The BBC is not responsible for the content of external sites. Read more.

This page is best viewed in an up-to-date web browser with style sheets (CSS) enabled. While you will be able to view the content of this page in your current browser, you will not be able to get the full visual experience. Please consider upgrading your browser software or enabling style sheets (CSS) if you are able to do so.

Americas Africa Europe Middle East South Asia Asia Pacific