Leisure centre handover concern
Works starting
Work started on the DG One leisure complex in August 2006
A 17.2m leisure development in Dumfries could miss its target date for handover to council control.

The DG One project has already slipped about six months behind its original building schedule.

However, the keys for the complex had been expected to be handed to the local authority on Friday.

It now appears that "snagging issues" - including repairs to the games hall floor required after a sprinkler system test - will force another delay.

It had been intended to open the DG One development in autumn 2007, but that date has been shifted several times.

The latest opening target is for the end of March.

A meeting will now be held to hear what can be done to achieve this schedule.

Leisure complex sub committee chairman David McKie said he was "deeply concerned" by the situation.

He said the authority would do everything in its power to ensure contractors Kier Northern did not miss the Friday deadline.

SEE ALSO
Leisure centre opening date doubt
29 Jan 08 |  South of Scotland
16.5m centre faces fresh delay
29 Oct 07 |  South of Scotland
Centre's handover date scheduled
25 Oct 07 |  South of Scotland
Leisure works 'in final stages'
19 Sep 07 |  South of Scotland
Prominent sites put in spotlight
21 Aug 07 |  South of Scotland
Leisure works get 15-week target
17 Aug 07 |  South of Scotland

RELATED INTERNET LINKS
The BBC is not responsible for the content of external internet sites



FEATURES, VIEWS, ANALYSIS
Has China's housing bubble burst?
How the world's oldest clove tree defied an empire
Why Royal Ballet principal Sergei Polunin quit

PRODUCTS & SERVICES

Americas Africa Europe Middle East South Asia Asia Pacific