Page last updated at 09:48 GMT, Wednesday, 4 November 2009

MSPs to consider funicular report

CairnGorm Mountain funicular railway
The building and operation of the funicular has run to £26.75m

A report on the financing of the Cairngorms' funicular railway was due to be considered by the Scottish Parliament's public audit committee.

Public spending watchdog Audit Scotland's report followed its investigation of Highlands and Islands Enterprise's backing of the project.

Since construction work started in 1999, the building and operation of the funicular has run to more than £26.75m.

Most of the funding has come from HIE which has spent £19.42m.

HIE has said the funicular was a key element of attempts to regenerate tourism in the area.

'Speculative' costs

In its report, Audit Scotland said the railway had met expectations of creating employment and attracting tourists.

But prior to construction, the watchdog said HIE had been focused on the project's design and controlling costs but had not taken account of, or reviewed, changes affecting skiing and operator CML.

According to Audit Scotland, a decline in skiers was among risks to the project not taken into account before it was built.

At the time the number of skiers using slopes in the Cairngorms was in decline.

In 1997, 97,000 skiers used Cairngorm but this fell to 75,000 in 1998, according the report.

The business case put together in support of the project had assumed 186,000 ski visitors per year.

CML was also struggling financially, said Audit Scotland.

In 1997 and 1998, the company reported losses of £607,000 and £625,000.

Also contained in the report are the £30m-£50m "speculative" costs of shutting down the railway and dismantling it.

Opened in 2001, construction cost £19.5m - almost £5m more than expected - but the total costs have since run up to £26.75m.

Most of the funding has come from HIE, followed by £3.26m from the Bank of Scotland, £2.61m of European Union grant aid, £1m from Highland Council and £100,000 from the Cairngorm Trust.



Print Sponsor


SEE ALSO
Risks to funicular 'not reviewed'
08 Oct 09 |  Highlands and Islands
Auditor to probe railway funding
10 Nov 08 |  Highlands and Islands
HIE takeover of mountain railway
19 May 08 |  Highlands and Islands
Takeover plan for mountain firm
09 May 08 |  Highlands and Islands
Ski centre achieves winter target
12 Apr 08 |  Highlands and Islands
Plan to build 'Eden of the North'
30 May 07 |  Highlands and Islands
Cairngorm Estate transfer on hold
29 May 07 |  Highlands and Islands

RELATED BBC LINKS

RELATED INTERNET LINKS
The BBC is not responsible for the content of external internet sites


FEATURES, VIEWS, ANALYSIS
How US failed to join dots in jet bomber case
Eye-catching images from around the world
Questions surround release of British hostage in Iraq

Explore the BBC

BBC © MMIX

The BBC is not responsible for the content of external internet sites.

This page is best viewed in an up-to-date web browser with style sheets (CSS) enabled. While you will be able to view the content of this page in your current browser, you will not be able to get the full visual experience. Please consider upgrading your browser software or enabling style sheets (CSS) if you are able to do so.
Americas Africa Europe Middle East South Asia Asia Pacific