Last Updated: Wednesday, 19 July 2006, 10:12 GMT 11:12 UK
Hot spots delay Dounreay clean-up
Dounreay
The total cost of decommissioning Dounreay will run to 2.9bn
A clean-up of part of the Dounreay nuclear plant in Caithness has been delayed after the discovery of higher than expected levels of radiation.

An underwater camera survey detected unexplained hot spots in a pond containing spent fuel used in the Dounreay Material Test Reactor (DMTR).

The find has meant plans to drain the pond have been put on hold until a follow-up probe has been carried out.

A spokesman for the 140-acre site said no-one has been put at risk.

Industry regulators have been informed.

A massive clean-up and regeneration project is under way at Dounreay, which is managed by the UK Atomic Energy Authority (UKAEA).

The UKAEA said the priority was to decommission and demolish the site as quickly and safely as possible.

The target of completion has been reduced from 2063 to 2033.

The 25 megawatt DMTR was Scotland's first operational reactor in 1958 and ran for 11 years.


SEE ALSO
Nuclear plant gets local feedback
12 Jul 06 |  Highlands and Islands
Public have say over nuclear site
05 Jul 06 |  Highlands and Islands
Workers remove nuclear concrete
21 Jun 06 |  Highlands and Islands
Waste leak contained at Dounreay
14 Jun 06 |  Highlands and Islands

RELATED INTERNET LINKS
The BBC is not responsible for the content of external internet sites



FEATURES, VIEWS, ANALYSIS
Has China's housing bubble burst?
How the world's oldest clove tree defied an empire
Why Royal Ballet principal Sergei Polunin quit

PRODUCTS & SERVICES

Americas Africa Europe Middle East South Asia Asia Pacific