Second cable inspection under way
Forth Road Bridge east side cable inspected
Inspectors are testing for corrosion on the cable
The second of the two main cables on the Forth Road Bridge has been wedged open to make way for inspectors to examine its thousands of wires.

They are assessing how much damage the east cable has sustained in the four years since it was last opened to be examined. Results are due in April.

Last week dehumidification equipment installed on half of the west side cable was switched on.

It is the first time such work has been carried out on a structure in the UK.



SEE ALSO
Bridge dry-out system switched on
22 Feb 08 |  Edinburgh, East and Fife
Work 'possible' on bridge cables
01 Jun 07 |  Edinburgh, East and Fife
Bridge wires snap 'one a month'
17 Jan 08 |  Edinburgh, East and Fife
New bridge to be built over Forth
19 Dec 07 |  Edinburgh, East and Fife
Bridge study on cable replacement
15 Aug 06 |  Edinburgh, East and Fife

RELATED INTERNET LINKS
The BBC is not responsible for the content of external internet sites



FEATURES, VIEWS, ANALYSIS
Has China's housing bubble burst?
How the world's oldest clove tree defied an empire
Why Royal Ballet principal Sergei Polunin quit

PRODUCTS & SERVICES

Americas Africa Europe Middle East South Asia Asia Pacific