Ministers ground airport PFI deal
Inverness Airport
The airport terminal cost 9.6m to build
Ministers have approved a deal to end the private finance initiative (PFI) agreement at Inverness Airport.

The 9.6m project saw the construction of a new terminal without any public money being spent up-front.

However, operator Highlands and Islands Airports Ltd had to pay finance company Inverness Air Terminal 3.50 for every passenger flying from the airport.

The leaseback agreement, which had been due to run until 2024, attracted widespread criticism.

It was branded a tax on expansion and denied Highland and Islands Airports the chance to negotiate cut-price deals with budget airlines.

Inglis Lyon, the airport operator's managing director, said a settlement price for the buy-out from the PFI owner, Infrastructure Investors, still had to be finalised.

The buy-out of the contract follows a similar move by the Scottish Executive last December to end tolls on the Skye Bridge.

Fundamentally flawed

Opponents of private finance initiatives for major public projects said the airport deal was further proof that the system did not work.

Fergus Ewing, Scottish National Party transport spokesman, branded the PFI deal "inept".

The Inverness East, Nairn and Lochaber MSP said: "The terminal originally cost 9.6m, however after only six years the PFI repayments have almost equalled that and the PFI owners are expected to receive a lottery-style payout of more than 25m.

"The PFI owners are therefore expected to have received around 36m. If so, they will have received four times as much as the building actually cost."

The current contract has clearly been holding back the development of the airport and the economic potential of the whole area
Nicol Stephen
Transport Minister

Mr Ewing said the deal was fundamentally flawed because the PFI owners received 3 for every new passenger who passed through the airport.

Transport Minister Nicol Stephen said: "This deal will have a major impact on the economy right across the Highlands and Islands.

"The current contract has clearly been holding back the development of the airport and the economic potential of the whole area."

Mr Stephen said the aviation market had changed since the PFI contract was signed in 1998.

"As a result of the advent of low cost flights the costs of the contract have significantly increased," said the minister.

"Every additional passenger made the current contract more expensive.

"This is why this buy-out deal will be good value for money."




SEE ALSO:
Airport PFI deal set for buy-out
25 Jan 05 |  Scotland
Tolls abolished for Skye Bridge
21 Dec 04 |  Scotland
Numbers soar at remote airports
17 May 04 |  Scotland


RELATED BBC LINKS:

RELATED INTERNET LINKS:
The BBC is not responsible for the content of external internet sites


PRODUCTS AND SERVICES

News Front Page | Africa | Americas | Asia-Pacific | Europe | Middle East | South Asia
UK | Business | Entertainment | Science/Nature | Technology | Health
Have Your Say | In Pictures | Week at a Glance | Country Profiles | In Depth | Programmes
Americas Africa Europe Middle East South Asia Asia Pacific