M74 project faces year-long delay
M74
The stretch of road will link the M74 and the M8
The controversial 500m project to extend the M74 in Glasgow will be delayed by up to a year because of legal action by opponents.

Ministers decided in March to press ahead with the scheme, despite a public inquiry which recommended that it should not proceed.

Friends of the Earth Scotland and Joint Action Against the M74 (Jam74) lodged an appeal against the decision.

It has emerged that work is now unlikely to start until June 2007.

The project is expected to take about two-and-a-half years to complete.

Public inquiry

It had originally been envisaged that the link would be finished by the end of 2008.

The new road would follow a route from the Fullarton Road Junction near Carmyle to the M8 just west of the Kingston Bridge.

In March the executive said it was planning to go ahead with the project - despite the recommendation of a public inquiry reporter.

What we are attempting to do is prevent 500m of taxpayers' money from being wasted on yet another pointless and environmentally-damaging motorway project
Duncan McLaren
Friends of the Earth Scotland

Last month those campaigning against the link lodged papers with the Court of Session in Edinburgh.

Opponents claim the scheme will create more traffic and pollution and say the executive has failed to give adequate reasons why it disagreed with the inquiry's conclusions.

Friends of the Earth Scotland's chief executive, Duncan McLaren, said it wanted the court case to be dealt with as quickly as possible.

"The communities affected by this massive scheme have already suffered blight as a result of this motorway proposal for far too many years," he said.

"The best way for the executive to end that blight would be to drop the proposal for good.

Reduce congestion

"What we are attempting to do is prevent 500m of taxpayers' money from being wasted on yet another pointless and environmentally-damaging motorway project."

The executive believes the extension will create 12,000 jobs, reduce congestion and cut road traffic injuries by up to 50 a year.

The road project has the support of business leaders and motoring organisations.




SEE ALSO:
M74 protesters in legal challenge
05 May 05 |  Scotland
Executive defends M74 land deals
11 Apr 05 |  Scotland
M74 protesters vow to fight link
28 Mar 05 |  Scotland
M74 opponents plan direct action
25 Mar 05 |  Scotland
Legal threat after M74 decision
24 Mar 05 |  Scotland


RELATED INTERNET LINKS:
The BBC is not responsible for the content of external internet sites


PRODUCTS AND SERVICES

News Front Page | Africa | Americas | Asia-Pacific | Europe | Middle East | South Asia
UK | Business | Entertainment | Science/Nature | Technology | Health
Have Your Say | In Pictures | Week at a Glance | Country Profiles | In Depth | Programmes
Americas Africa Europe Middle East South Asia Asia Pacific