MPs lose faith in millennium tube plans

MPs fear the connection to the Millennium Dome will not be ready on time

Transport chiefs have been criticised by MPs after setting a "last minute date" - the end of October 1999 - to finish the Jubilee Line in time for the opening of the Millennium Dome.

Denis Tunnicliffe, London Transport's chief executive, was criticised by a Commons Select Committee for not having contingency plans in the event of the extended underground line not opening in time.

Mr Tunnicliffe admitted the effect of the Millennium Dome celebrations, set to attract 70,000 visitors a day, would be "dire" if the extension was not completed.

He said: "We will take steps to make a contingency plan at an appropriate time if we are unable to adhere to the promised objective."

In a two-hour session with the Culture, Media and Sport Committee he was told the panel of MPs had "lost faith" in his latest completion forecast.


[ image: A year ago MPs were told the connection might be completed by September 1998]
A year ago MPs were told the connection might be completed by September 1998
Gerald Kaufman MP read minutes from the committee inquiry with London Transport exactly a year ago in which Mr Tunnicliffe promised the line would be completed by September 1998.

Mr Kaufman said: "You told us there was definitely a 'better than even' chance of the line opening by the end of September 1998.

"We are now a year on from that. You are now asking us to have faith. Why should we have any greater confidence?

"My faith is rapidly diminishing."

Mr Tunnicliffe, who rejected a call from Christopher Fraser MP to resign for his handling of the project, blamed current industrial action by electricians and complex work on the project for the further delays.

The strategy for opening the Jubilee extension has been dogged by delays.

London Transport changed from opening the extension as a whole in September 1998 to Spring 1999, and now to one of opening in three phases during the period of Spring to Autumn 1999.

The date of completion of the three phases set by London Transport are:

  • Phase 1 - Stratford to North Greenwich - spring 1999

  • Phase 2 - Stratford to Waterloo - end of August 1999

  • Phase 3 - Stratford to Green Park - end of October 1999.



    Advanced options | Search tips




    Back to top | BBC News Home | BBC Homepage |


  • UK Politics Contents

    A-Z of Parliament
    Talking Politics
    Vote 2001
    In this section

    Livingstone hits back

    Catholic monarchy ban 'to continue'

    Hamilton 'would sell mother'

    Straw on trial over jury reform

    Blairs' surprise over baby

    Conceived by a spin doctor?

    Baby cynics question timing

    Blair in new attack on Livingstone

    Week in Westminster

    Chris Smith answers your questions

    Reid quits PR job

    Children take over the Assembly

    Two sword lengths

    Industry misses new trains target