Tuesday, October 12, 1999 Published at 08:22 GMT 09:22 UK
UK: Scotland Bridging the Kingston gap ![]() The bridge is one of the busiest crossings in Europe Strathclyde Police are mounting their biggest traffic management operation ahead of the Kingston Bridge closing for vital repairs. More than 200 officers are involved in the huge operation. The 50,000-tonne bridge, one of Europe's busiest river crossings, carries 150,000 vehicles a day over the Clyde.
On both weekends the bridge and the M8 will be closed for 35 hours from Junction 19 (Anderston) to Junction 21 (Seaward Street) in both directions between 1900 on Saturday and 0600 on Monday.
Glasgow Council Transportation Manager Marshall Poulton said: "These diversions may be a little longer in terms of distance but will save on journey time and frustration especially if you are travelling beyond Glasgow. "This is particularly important for those travelling to Glasgow airport. "I should stress, however, that Glasgow will be open when the closures take place. If people set aside more time for their journeys these weekends and try to take alternative transport there is no reason why they can't complete their journeys on time." There will also be extra underground services and more carriages on many ScotRail trains on the Strathclyde network into Glasgow during the closures.
As a result, the bridge deck had slipped on its bearings and was pressing against the approach structures. Jacks will hold the bridge deck in place for seven months while the old support piers are demolished and new ones constructed under the deck, using reinforced concrete.
|
|
||||||||||||||||||||||||||||||||||||||||