Tunnel work complete 'next spring'
Bulges in the Saltash Tunnel
Hundreds of aluminium panels are having to be replaced
The refurbishment of the Saltash Tunnel, one of the main road links into Cornwall, will not be complete until next year.

The £7.5m contract should have been finished by March this year.

But a number of problems have delayed the project.

One of the main hold-ups has been the aluminium panels lining the tunnel walls.

Hundreds of them have buckled and bulged and are having to be replaced.

The Highways Agency had hoped the additional work would finished by the end of November.

But now says it will be spring next year before the work is finished, about a year behind schedule.


SEE ALSO:
Tunnel panels to be replaced
14 Aug 03  |  Cornwall
Tunnel walls bulging
22 Jul 03  |  Cornwall
Tunnel problems were predicted
28 Jun 03  |  Cornwall
Minister rejects tunnel criticism
18 Jun 03  |  Cornwall


RELATED INTERNET LINKS:
The BBC is not responsible for the content of external internet sites


PRODUCTS AND SERVICES

News Front Page | Africa | Americas | Asia-Pacific | Europe | Middle East | South Asia
UK | Business | Entertainment | Science/Nature | Technology | Health
Have Your Say | In Pictures | Week at a Glance | Country Profiles | In Depth | Programmes
Americas Africa Europe Middle East South Asia Asia Pacific